This page was printed from https://geosyntheticsmagazine.com

Rhode Island DOT replaces bridge in 80 hours using GRS-IBS technology; releases video

News | December 5, 2017 | By:

The Rhode Island Department of Transportation (RIDOT) began work on the McCormick Quarry Bridge in East Providence on Sept. 23, 2016, using a geosynthetic reinforced soil–integrated bridge system (GRS-IBS). According to the Federal Highway Administration and RIDOT, the technique allowed crews to cut the construction time for the bridge from one year to 80 hours.

Then Vice President Joe Biden visited the McCormick Quarry Bridge when he went to Rhode Island in May 2016 to see the state’s RhodeWorks infrastructure program in action. At that time, Biden called the stacked timber shoring installed to support the bridge’s structural load due to its severe concrete deterioration “Lincoln Logs.”

“When Vice President Biden visited Rhode Island, he was shocked at the condition of this bridge and the ‘Lincoln Logs’ necessary to hold it up,” Gov. Gina M. Raimondo said. “Thanks to RhodeWorks, [we replaced this deficient bridge and removed] a symbol of past inefficiencies in fixing our roads and bridges.”

The bridge replacement is part of a two-bridge project that will cost $16.7 million, including a $663,000 budget contingency. The McCormick Quarry Bridge was built in 1959 and had been structurally deficient for more than 20 years. It carries 17,000 vehicles per day.

During the closure, RIDOT demolished the McCormick Quarry Bridge and completed work on the foundations for the new bridge. They then installed the entire bridge’s superstructure (steel beams and concrete deck), which was built in temporary staging areas on top of large supports adjacent to the old bridge.

Once the bridge foundational elements were ready, RIDOT used large multi-wheel dollies to lift the new bridge off its supports, drive it down Warren Avenue, move it into position and lower it onto the new foundations. Finishing work to complete the riding surface between the bridge and the road segments on either side came next. RIDOT closed the bridge at 9 p.m. on Friday, Sept. 23, 2016; completed the entire operation; and reopened the bridge before 5 a.m. on Tuesday, Sept. 27, 2016.

“This rapid bridge construction approach lets us complete the job of replacing these deficient and obsolete structures as quickly as possible with as little impact as possible to the traveling public,” RIDOT director Peter Alviti Jr. said.

RIDOT released a time-lapse video of the project, which can be viewed at http://bit.ly/2AVkt3E.

Share this Story

Leave a Reply

Your email address will not be published. Required fields are marked *

Comments are moderated and will show up after being approved.