Canal construction finalized with geocell stability
Geosynthetics | February 2010
Introduction
The primary objective of this project was to protect the banks of a canal that was constructed in front, and throughout the grounds, of a new luxury hotel in Panama.
Bristol Buenaventura Resort, located approximately 85 miles west of Panama City on the Pacific Ocean coastline, opened in 2009. The manicured grounds include walking paths and gazebos strategically placed amid a winding, man-made canal.
The complete site preparation, all installations, and final finishing work were completed in about three weeks by local gardeners.
Potential problems
This new construction of a man-made, vegetated canal for an upscale beach resort required wall slope angles of 1:1 to 3:1, potentially unstable, and the construction schedule was fast-tracked including propagation of the vegetation.
The site plan called for a geotextile that was installed initially across the entire working area. Then the geocell layer was put in place. The geocell infill was local sand and sandy soil. Then sod was placed on the top of the geocell/soil layer.
Likely solutions
The key component for the contractor was the 4-in. perforated geocell material, filled with native sandy soil to stabilize the slopes.
First, a nonwoven geotextile was put in place, to serve as a separator and to impede erosion between the layers. Then the geocell layer was installed. After the geocells were in place, with the slopes stabilized, sod was then laid directly on top.
Installation of the 4,000m2 of geocells, and putting the sod in place, took an eight-man crew about five days.
Geosynthetics encourages your contributions of case histories, photos, and field tips. For submittal guidelines, contact Ron Bygness at 800 225 4324 or +1 651 225 6988; e-mail: rwbygness@ifai.com
-
This project was designed and completed to protect the banks of a man-made canal at a new resort in Panama. -
The man-made canal required slope angles of 1:1 to 3:1, potentially unstable, so a geotextile/geocell design was implemented. -
The man-made canal required slope angles of 1:1 to 3:1, potentially unstable, so a geotextile/geocell design was implemented. -
The plan called for a nonwoven geotextile in place across the working area, then the installation of a geocell layer. -
The plan called for a nonwoven geotextile in place across the working area, then the installation of a geocell layer. -
With the geotextile in place for separation and erosion control, the geocell layer was placed with infill of local sand and soil. -
With the geotextile in place for separation and erosion control, the geocell layer was placed with infill of local sand and soil. -
With the slopes stabilized by 4,000m2 of geocells, the sod placement completed the job. -
With the slopes stabilized by 4,000m2 of geocells, the sod placement completed the job.




Comments
There are not yet any comments.
You can submit a comment using the form below.
Submit a Comment