Reinforced roads needed at wind farm

Share This Article

  • Del.icio.us
  • Digg
  • Facebook
  • Google Bookmark
  • StumbleUpon
  • Technorati
  • Twitter

Tags

A massive wind farm project just south of Glasgow, Scotland, eventually will have 140 2.3-megawatt turbines in operation. But before the turbines could be erected, construction roads over peaty soils had to be built.

“We lay a geotextile mat and geogrid reinforcements across the peat before creating the road,” said Anthony Windle, project manager for the principal contractor on the job. A 600mm layer of graded rock is added to the geotextile/geogrid combo to shore up the structure, topped by 200mm of crushed rock.

When completed in the summer of 2009, the Whitelee Wind Farm is projected to provide around 180,000 homes with electricity.

Comments

There are not yet any comments.
You can submit a comment using the form below.


Submit a Comment

Required. Will appear next to your comment.
Required. Will not be displayed on site or used to send unsolicited messages.
If applicable. A link to your site will appear with your comment.
Optional. Will appear in bold type above your comment.